1/17/11 How's that industrial wind turbine thing working out? Like a bad neighbor, Acciona is there. AND Perception VS. Reality: Putting the Green Spin on Wind Energy AND Wind Lobbyist's tantrum about Walkers proposed setbacks AND Extra Credit Reading List

WAUBRA RESIDENT TELLS COURT OF WIND FARM "HELL"

SOURCE The Courier, www.thecourier.com.au

January 18 2011

Former Waubra resident Trish Godfrey yesterday told an Adelaide court how her dream home became “hell on earth” after wind farm turbines were turned on.

Ms Godfrey said she suffered sleep deprivation, headaches and nausea before moving out in April 2010 when Acciona purchased her property.

“It was like you had a hat on that’s too tight and you have a pain that just gets worse and worse, and you can’t take it off,” Ms Godfrey said. “There was pain most of the time.”

Ms Godfrey broke down in tears as she gave evidence at the Environment Resources and Development Court.

Dairy farmer Richard Paltridge is appealing a decision to grant Acciona approval to build a 46-turbine wind farm near his property, south of Mt Gambier.

Ms Godfrey said her symptoms began about a month after turbines were turned on, then got progressively worse.

“I said to my husband I’m not sick but I don’t feel well,” she said.

“It felt like I had a cold coming on all the time.

“My sleep patterns were changing. I was waking up two, three, four times a night. I couldn’t explain it. I couldn’t get my head around what was going on.

“You put it down to everything but what it is.”

Ms Godfrey said she and her husband Victor, a dental surgeon, went on holiday to Darwin and the symptoms stopped, then resumed when she returned home.

“You get back and it starts all over again,” she said. “It all came back with gusto.”

Under questioning by George Manos for Mr Paltridge, Ms Godfrey said the 10-acre property was her “dream” home, where she and her husband intended to retire.

She said she planted 750 to 1000 boundary trees, about 30 fruit trees and 17 vegetable beds in the 10 years they lived there.

Ms Godfrey said she had been led into a false sense of security in a meeting with David Shapiro of Wind Power, the company that set up the Waubra project and sold it to Acciona.

“He told us there would be a couple of turbines on Quoin Hill, a couple on Big Hill and a few behind us,” Ms Godfrey said.

“He said there would be no lights, no wires and no noise.”

Ms Godfrey said 63 turbines could be seen from her property and it became “hell” to live there.

She said the noise “pressed in” on their home. “It was anywhere from a low whooshing sound, a sweeping swoosh some days, and when the wind was coming from the north it was like a jumbo jet in the back paddock,” she said.

Former Waubra resident Carl Stepnell told the court yesterday he and his wife’s symptoms of chest pains, heart palpitations and sleep deprivation ceased after the couple moved away from the family farm to Ballarat in November.

“We feel as though we’ve got our health back,” Mr Stepnell said.

Mt Stepnell said his wife also suffered depression while living close to the turbines.

“Her whole appearance … it was scary to see how bad she was,” he said. “She was really down, depressed … shocking.”

Mr Stepnell said his five-year-old son attended Waubra Primary School until the family moved.

“I see a big difference in his behaviour,” he said.

“He is nowhere near as emotional … he was pale. (Now) he’s like a normal five-year-old.”

SECOND FEATURE

PERCEPTION VS REALITY

SOURCE: he Republican-American, www.rep-am.com

January 16,  2011

By Bill Gregware,

Wise people (and politicians) often say perception is more important than reality. Take the case of wind energy in Connecticut. What are the perceptions and what are the realities? With the proposed wind projects in Colebrook and Prospect currently being so hotly debated, perhaps it’s timely to consider a few points.

Wind power will lower the cost of electricity. The promoters of wind power frequently start their pitch by saying Connecticut has the highest rates for electricity within the continental United States. That is true, and the target audience often comes away with the impression more wind power will mean a decrease in electricity costs.

The reality is electricity generated from wind is much more expensive than that produced from traditional sources. It’s often stated wind-generated electricity costs 15 percent to 20 percent more than does that generated by coal, but the actual cost may be even more. It is difficult to calculate because of the variables involved. Only in rare cases is it lower than 15 percent more than coal-generated electricity. And with wind power, consumers not only pay higher prices for electricity, they are, as taxpayers, also paying for the generous subsidies this industry is receiving. Without subsidies there is simply no way wind power can compete economically.

 Oil imports will be reduced. A misleading perception is that more wind turbines will reduce our dependence on foreign oil imports. The American Wind Energy Association (AWEA) says, “Unlike the dirty energy from fossil fuels, wind energy does not cause … dependence on unfriendly foreign regimes.”

In reality, wind energy may not cause the dependence but does nothing to reduce it. The majority of the electricity produced in the United States is derived from domestic sources: coal, about 45 percent; natural gas, 25 percent; nuclear, 20 percent; and hydroelectric, 6 percent, not from burning fossil fuels imported from other nations.

The danger in promoting such claims is that it leads the public into thinking something positive is being done to curb oil imports and this very serious problem is being solved. People are then less apt to support the implementation of projects that could improve the environment and reduce imports of oil, such as increasing emphasis on efficiency and conservation.

 Environmentalists support wind power. The promoters of wind power make every attempt to show “true environmentalists” support wind power while opponents are anti-green. The truth is growing numbers of hard-core environmentalists are becoming disillusioned with wind power.

In his book “The Wind Farm Scam,” Dr. John Etherington, a highly esteemed UK ecologist and beyond doubt an avid environmentalist, wrote: “The specter of climate change is being used as a scare tactic to get people to buy wind power. This is the old quack-doctor trick — scare them to death and they’ll buy anything. It (wind power) will certainly be seen by history as a swindle supported by untruths and half truths.”

 Property values are unaffected by wind turbines. The wind industry has taken a hard-line approach to the property-value question. It often presents detailed reports by “experts” that indicate property values do not decrease in the vicinity of wind turbines. Most of these reports are written by wind advocates using flawed data and reaching invalid conclusions.

The answer to the property-value question is found in common-sense reasoning. Who, given a choice, would want to live near these devices? How many potential buyers would seek homes in the vicinity of a wind turbine? For that matter, how many executives of the wind industry live near turbines?

Numerous anecdotal stories tell of folks being unable to sell their homes and abandoning them because they could no longer tolerate the noise or other characteristics of turbines.

Wind power will replace dirty power plants. “U.S. winds contain enough energy to provide over 10 times our total electricity, and to fuel a large portion of our auto fleet with electricity as well,” says the AWEA, giving the perception we can eliminate existing conventionally powered plants.

Think of that! All we have to do is to cover our countrysides with wind turbines and the dirty old coal plants can be shut down, with enough electricity will be left over to fuel electric cars. The problem is the intermittent nature of wind means it must have backup. Wind turbines have never replaced a traditional power plant.

Wind power means jobs. Jobs are created by the wind industry, but that can be said of any industry. The perception the promoters try to depict is that wind power means a great many new jobs for local workers. However, most of the work is in the manufacture of the turbines, which is done far away from the site, perhaps even in a foreign land. And once they are in place, turbines require little manpower except for once a year or so routine maintenance.

Why does the wind industry work so hard hawking half truths and hyperbole to create false perceptions that wind power is so wonderful, even in relatively low-wind areas like Connecticut?

It’s because a bad idea is difficult to sell. The reality is that wind power is not about “going green.” It’s all about money.

Bill Gregware (gregwarebill@hotmail.com) of Goshen is a retired oil company geologist/exploration manager. He is also an avid environmentalist and freelance writer who specializes in writing about nature and energy. Further, he is a party to those fighting the proposal by Optiwind to build a turbine in Goshen.

THIRD FEATURE

SOURCE: WindAction Editorial

Denise Bode, Head of AWEAAWEA has a tantrum -- again

(Posted January 16, 2011)

EXTRA CREDIT: CLICK TO READ....

What's this about 'clean' wind energy's toxic footprint?

Last week it was reported that China - which has a global monopoly on the production of rare-earth metals - is now threatening to cut off vital supplies to the West. A shortage would jeopardise the manufacturing and development of green technologies such as wind turbines and low-energy lightbulbs.Last week it was reported that China - which has a global monopoly on the production of rare-earth metals - is now threatening to cut off vital supplies to the West. A shortage would jeopardise the manufacturing and development of green technologies such as wind turbines and low-energy lightbulbs.

12/30/10 VIDEOS OF THE DAY: Rock out to wind turbine construction AND then try to live with turbine noise AND Who cares about birds getting killed by wind turbines when there is so much money to be made? AND You break it, you pay: Wind project residents mandate property value guarantee AND Like a bad neighbor... Acciona is there

OUR WIND INDUSTRY VIDEO OF THE DAY:

Click on the image below to watch a happy wind developer talk about his project. Note the lack of homes in this video. Also note the compression of the soil and other side effects of the heavy machinery required during turbine construction. Rock out to the guitars in the background.

OUR REALITY VIDEO OF THE DAY

Life with turbines: Click on the image below to hear the turbine noise from a wind project home in DeKalb, Illinois. Recorded December 17th, 2010

WIND DEVELOPMENT THREATENS ICONIC AMERICAN BIRDS

SOURCE www.salem-news.com

December 29 2010

Safeguards needed to prevent population declines in the Whooping Crane and Greater Sage-Grouse, and reduce mass mortality among eagles and songbirds.

(LOS ANGELES) – Today, American Bird Conservancy announced that three iconic American bird species face especially severe threats from wind energy development.

“Golden Eagles, Whooping Cranes, and Greater Sage-Grouse are likely to be among the birds most affected by poorly planned and sited wind projects,” said Kelly Fuller, Wind Program Coordinator for American Bird Conservancy, the nation’s leading bird conservation organization.

“Unless the government acts now to require that the wind industry respect basic wildlife safeguards, these three species will be at ever greater risk.”

The U.S. Fish and Wildlife Service (FWS) currently estimates that more than 400,000 birds are already being killed each year after being struck by the fast-moving blades of wind turbines.

This figure is expected to rise significantly, and will likely eventually pass the million mark as wind power becomes increasingly ubiquitous under a Department of Energy plan to supply 20% of America’s power through wind by 2030.

Golden Eagles have already been one of the major victims of the largest wind farm in the United States at Altamont Pass in California. The Altamont wind farm was sited in an area that eagles and other raptors use to hunt ground squirrels and other small mammals.

Using the now-outdated towers as perches, thousands of raptors have been killed as they launch out through the spinning turbines towards their prey. While new tower designs have been developed, they don’t completely eliminate the risk.

Much of the additional wind build-out planned for the western U.S. is expected to occur in areas used by Golden Eagles.

A further threat to birds is expected to come from the major transmission line build-out required to service new wind farms. Large birds such as the endangered Whooping Crane can fail to see the wires in time and die after colliding with them. According to a recent FWS report, “The Great Plains states traversed by the Whooping Cranes during their fall and spring migrations are among the windiest states in the nation.

The best places for wind energy development in these states overlap to a large extent the Whooping Crane migration corridor, and many of these areas provide attractive stopover sites. Thus, the potential for impacts to Whooping Cranes from future wind energy development is high.”

The threat to yet more birds comes not from collisions, but from loss of their habitat due to wind farm construction. The Greater Sage-Grouse is already reduced to a tiny fraction of its former range and population size due to degradation of sagebrush habitat in the West.

The proliferation of giant turbines looming over the habitat can cause birds to abandon remaining traditional breeding grounds. The total habitat footprint from wind farms is predicted to exceed 20,000 square miles by 2030, much of it in states such as Wyoming, one of the last remaining sage-grouse strongholds.

While the threat from wind development stands out for these three iconic American birds, it is by no means limited to a small handful of species. More than ten billion birds are estimated to migrate across the country each spring and fall, many at night.

Wind turbines will be an unexpected obstacle to these migrations. Plans to build a wind farm at Canada’s Point Pelee—a migration hotspot on the Great Lakes—were recently shelved due to a public outcry over the expected impact on songbirds, but other wind developments are planned along the U.S. side of the lakes, and in other areas through which migrating birds funnel, with as-yet uncalculated bird impacts.

While Whooping Cranes are protected under the Endangered Species Act and Golden Eagles under the Bald and Golden Eagle Protection Act, most migratory birds are only protected by the Migratory Bird Treaty Act, which has seldom been enforced to prevent such mortality as is predicted as a result of wind development.

The Greater Sage-Grouse, meanwhile, currently receives no federal legal protection, though several states have stepped up to protect remaining core breeding areas. In the face of increasing wind development, realizing the potential for state agencies to do yet more will be important for this species.

“Without strong standards designed to protect birds through smart siting, technology, and mitigation programs, wind power will soon affect millions of birds. Given the subsidies paid to the wind industry by the government, many of the negative impacts to birds will be unwittingly funded by the American taxpayer,” said Fuller. “We understand the problem and we know the solutions. American Bird Conservancy supports wind energy, and some operators are already working to protect birds, but we need to make all wind power bird smart now before major build out occurs.”

SECOND FEATURE:

HAMMOND WIND PANEL ADOPTS HOME GUARANTEE

 SOURCE The Journal, www.ogd.com 

December 30 2010

By Matt McAllister,

HAMMOND – Is the Hammond Wind Committee nailing the coffin on the town’s chances of hosting an Iberdrola-owned wind farm?

The committee voted 9 to 1 Tuesday evening – with committee member and leaseholder, Michele W. McQueer, casting the lone dissenting vote – to adopt the controversial Residential Property Value Guarantee (RPVG) as a suggestion to the town board.

In a recent letter from Iberdrola Renewables to the committee, Mark Epstein, Esq., senior counsel, wrote, “We believe that if the Committee chooses to pursue the RPVG, it will prevent any development of windpower facilities in Hammond.”

Iberdrola Communications Manager Paul Copleman e-mailed the following statement on Wednesday: “We are disappointed in the Committee’s decision to recommend the Residential Property Value Guarantee in its current form. While we appreciate and welcome the Committee taking a close look at the concerns expressed by some community members, we have explained the significant and potentially prohibitive burden such a RPVG would place on both members of the community and any company wishing to open a business in Hammond.

“We look forward to continuing to work with the Committee, but most likely won’t reach any decision about the project’s viability until Hammond adopts zoning laws governing wind energy.”

The agreement, drafted by Richard K. Champney, committee member and real estate attorney, was reviewed over the past several weeks by all committee members, who offered their suggestions. Many members of the public were also considered, according to Mr. Champney, who said he had received a horde of phone calls and e-mails, none of which offered opposition to his proposal.

After a lengthy discussion, a motion was made by Merritt V. Young and seconded by Ronald R. Papke.

The revised document includes changes in Section 13, “Exclusive option of any residential property owner living within close proximity (two miles) to a wind turbine,” where a property owner has a once in a lifetime right to be reimbursed for his or her real property and five acres surrounding that residence at the then appraised value, if they follow the provisions listed in the document.

These provisions now include:

* Property owner must notify guarantor within 90 days of issuance of an industrial wind farm permit;

* Property owner must have been the legal owner of real property at the time permit was issued;

* Property owner and the guarantor will enter into a 30-day cooling off period where property owner discusses entering into a Good Neighbor Program and if it is not possible, they will continue to complete the agreement application;

* Guarantor will consider relocating wind turbine out of a two-mile radius of the property owner’s residence;

* If property owner and guarantor have not reached agreement within 60 days, the property owner orders a certified property appraisal that can be used as cost replacement value;

* If still no agreement, a second and/or even a third appraisal can be ordered which will then be averaged with the first to determine the final controlling value the property owner will receive as a buyout from the guarantor (wind company). This option cannot be used in conjunction with any future guarantee of the sale of a residence.

In further discussion before moving on to the next issue, there was mention made of a Good Neighbor Agreement that Iberdrola representative, Jenny Burke, had just made available to committee members which was apparently offered as an alternative to the RPVG.

Good Neighbor Agreements are made between non-participating land owners in the vicinity of wind turbines and the wind company, according to Ms. Burke, and can involve either monthly or annual payments in exchange for closer proximity. In response to a question from committee member, Frederick Proven, Ms. Burke said such agreements typically apply to anyone living within 3000 feet of a wind turbine but that it hadn’t been decided for this particular project because a turbine layout has not yet been established.

Mr. Champney said that a landowner could not apply for both agreements, as it would constitute “double dipping.” He said he would be willing to hold a complimentary workshop for landowners to help them understand the ramifications of a Good Neighbor Agreement.

Members discussed property management issues that included oversight of the wind project, decommissioning, and insurance and liability issues.

Board members also discussed the wind overlay district and attempted to clarify how it applies to the waterfront. Several committee members felt that rather than starting at Route 12, it should begin at the St. Lawrence River shoreline. This discussion will continue Tuesday at 7 p.m. in the Hammond Central School Library, with additional agenda items to include economics and tourism, setbacks and environmental issues.

THIRD FEATURE

WIND FARM PLAN CHALLANGED

SOURCE The Border Watch, www.borderwatch.com.au

December 30 2010

Anelia Blackie,

An eight Mile Creek landowner is furious after learning his house would be within 750 metres of wind turbines if the proposed wind farm development goes ahead at Allendale East.

The Acciona Energy project has been temporarily stalled pending the outcome of a court decision after Allendale East dairy farmer Richard Paltridge opposed the development, standing alone in his battle against the company.

But in the past week, Paul Manning and his wife Kaeli have thrown their support behind Mr Paltridge — only to find out that up to 30 residents also share their objections, but chose to remain anonymous because they feared victimisation.

“We are a hard working young family — my partner has shed blood, sweat and tears to make that property what it is today,” Mr Manning told The Border Watch.

“She literally cried when she began to comprehend what the wind farm’s impact will have on our future plans, including the future development of our investment, our retirement, in terms of the potential for the property and the personal connection we have with it.”

According to Mr Manning, many of the landowners, including himself, do not live on their properties, but work interstate and were therefore ill-informed or excluded from a community consultation process about the $175m development.

He has joined the Concerned Residents Group fighting to have the consultation process re-opened.

“We are very disappointed and concerned at hearing about decisions and actions so detrimental to our family’s future,” Mr Manning said.

“The only previous communications we have received in regards to this very serious matter was a very simple and poorly copied generic pamphlet that was delivered nearly two years ago — we have received nothing since.”

“With gag orders on many of the neighbours and our current work interstate, we have heard little about the planning, design and impact of the wind farm.”

Mr Manning said the proposed wind farm added to other issues already looming over the community and causing them to lose confidence in Local Government.

“Through our recent investigations, one thing has become increasingly clear about the view the community has of the government at all levels,” he said.

“There is a real undercurrent of a no confidence vote brewing within the community due to the problems with the cray fishing season being shortened and all the forests and timber mills scheduled to be sold off to overseas interests — many jobs will be lost and the real talk is that the region will become a ghost town kept in a near death state by the humming and whirring of turbines — this has already been demonstrated at similar locations.”

10/23/10 Here Comes the Judge: 20 wind project residents could get their day in court AND State of Oregon decides to take wind project residents complaints seriously AND Like a bad neighbor, Acciona is there

DATES SET FOR WIND LAWSUIT

SOURCE: Huron Daily Tribune, www.michigansthumb.com

October 23 2010

By Kate Hessling, Tribune Staff Writer,

Turbines in Ubly, MichiganBAD AXE — Dates have been set for a case evaluation and jury trial for the lawsuit filed by 20 Huron County residents claiming the Ubly area Michigan Wind I development has harmed their quality of life and lowered property values.

Huron County Circuit Court officials said a case evaluation will be conducted July 21, 2011 and a jury trial has been scheduled for Oct. 4, 2011. The dates were set after a pretrial hearing that was held Thursday.

The case evaluation consists of a panel of three attorneys who will review the case and recommend a case outcome. The plaintiffs and defendants then will have 28 days to either accept or reject the results of the case evaluation. If both accept the recommendation, an order closing the case will be drafted. If one or both parties reject the recommendation, the case goes to a jury trial.

In the lawsuit, which was filed May 11 in Huron County Circuit Court against John Deere Renewables, Deere & Company (John Deere), Noble Environmental Power, LLC, Michigan Wind I, LLC (Noble Thumb Windpark I) and RMT, Inc., the plaintiffs are seeking in excess of $25,000 and an injunctive relief ordering the companies to cease and desist their activities.

The lawsuit consists of four counts: Private nuisance (Count I), public nuisance (Count II), negligent design of a wind farm (Count III) and negligent misrepresentation (Count IV). While the lawsuit names John Deere Renewables, John Deere, Michigan Wind I, LLC and Noble Environmental Power, LLC in all four counts, RMT, Inc. is named only in Count III.

In August, Huron County Circuit Court Judge M. Richard Knoblock dismissed two of four counts against John Deere Renewables, LLC, Deere & Company and Michigan Wind 1, LLC, and one of four counts against Noble Environmental Power, LLC

Knoblock’s ruling left John Deere, John Deere Renewables, Michigan Wind I LLC facing two counts: Count I of private nuisance and Count II of public nuisance. Noble Environmental Power, LLC is left with three counts: Count I of private nuisance, Count II of public nuisance and Count III of negligent design of a wind farm. RMT, Inc. still faces the one count of negligent design of a wind park.

In the lawsuit, the plaintiffs allege the actions of the wind companies and Michigan Wind 1 wind farm have caused the plaintiffs substantial damage, including, but not limited to, physical harm and adverse health effects, including the inability to sleep and repeated awakening during sleep, headaches, dizziness, stress and tension, extreme fatigue, diminished ability to concentrate, nausea and other physiological cognitive effects.

According to the answer attorneys for RMT, Inc. filed in response to the plaintiffs’ lawsuit, RMT denies it is liable to the plaintiffs in any amount of money whatsoever, and is asking the court to dismiss the complaint and grant RMT, Inc. its costs, attorney fees and whatever other relief the court deems appropriate.

Answers filed by attorneys for John Deere, Deere Renewables and Michigan Wind I LLC, and by attorneys for Noble Environmental Power, LLC, also deny the allegations in the lawsuit.

The plaintiffs in the case are David Peplinski, Marilyn Peplinski, Frank Peplinski, Georgia Peplinski, Terry Peplinski, Christine Peplinski, Curtis Watchowski, Lynda Watchowski, James Czewski, Delphine Czewski, Dennis Mausolf, Darcy Mausolf, Dale Laming, Elaine Laming, Lynn Sweeney, Pam Sweeney, Alger Nowak, Mary Nowak, Randy Weber and Angela Weber, according to court documents from the Huron County Clerk’s Office.

In the lawsuit, the plaintiffs allege the actions of the wind companies and Michigan Wind 1 wind farm have caused the plaintiffs substantial damage, including, but not limited to, physical harm and adverse health effects, including the inability to sleep and repeated awakening during sleep, headaches, dizziness, stress and tension, extreme fatigue, diminished ability to concentrate, nausea and other physiological cognitive effects.

The lawsuit attributes the adverse health effects to low frequency and sub-audible infrasound and/or impulse noise created by and emitted from turbines in the Ubly area wind park.

Noise and setback issues included in the lawsuit are what many opponents to local wind energy development say are the most contentious issues surrounding the Nov. 2 county Proposals 1 & 2. They believe the county’s standards are too lax and put the public health, safety and welfare at risk.

County officials and wind proponents have countered efforts urging people to vote “No” on the two proposals by noting the two proposals are not about noise and setbacks. The proposals are to amend the county’s wind ordinance to change two areas of the county — McKinley Township and portions of Rubicon, Sigel and Bloomfield townships — from a zoning classification of agriculture to a zoning classification of agriculture with a wind overlay district.

The proposals do not seek to change any of the ordinance’s language or existing noise and setback standards for wind energy developments.

With that said, opponents to wind developments say readers should be informed about these issues from Dr. Malcolm Swinbanks, the expert who wind opponents repeatedly have referenced in literature and public meetings.

Some key points of opponents and proponents in this debate will be featured in Tuesday’s edition of the Huron Daily Tribune.



SECOND FEATURE

OREGON PUBLIC HEALTH OFFICE DECIDES IT'S TIME TO STUDY HEALTH EFFECTS OF WIND TURBINES

By Scott Learn, The Oregonian, www.oregonlive.com 21 October 2010

Oregon has boosted wind energy projects with a vengeance in recent years, adopting a renewable power standard and tax breaks that have helped spread wind farms across the state’s northern reaches and into eastern Oregon.

Now comes the Oregon Public Health office, which announced Thursday that it’s embarking on a public health assessment of wind farms, kicking off with three “listening sessions” next month in LaGrande, Pendleton and Arlington to hear residents’ health concerns tied to the spinning blades.

The health issues are part of a broader backlash in Oregon and nationwide from critics who complain of negative impacts on scenery, property values, wildlife and tourism.

The growing number of wind farms has led to more complaints about their health effects, said Sujata Joshi, an epidemiologist in the environmental public health office. Health concerns raised to date focus on noise and vibration generated by the huge turbines.

The assessment will start with the listening sessions, but also include a review of health studies and talks with a steering committee that will include wind farm developers, community members, the state Department of Energy and Oregon’s energy facility siting council, which oversees new wind farm locations.

“With any development, you start learning more about potential concerns as more people start experiencing it,” Joshi said. “Our goal now is to hear what people have to say, and see if we can find solutions that work for communities and for the state’s goals.”

Wind farm critics cite work done by New York physician Nina Pierpoint who coined the term “wind turbine syndrome” to describe effects — such as headaches, dizziness and memory loss — of living near the machines. Industry representatives say they haven’t seen solid research linking wind turbines and negative health effects.

In May, Morrow County’s planning commission voted to give owners of the 72-megawatt Willow Creek farm six months to comply with state noise regulations. In November, Union County voters will vote thumbs up or down on the proposed Antelope Ridge Wind farm, though the vote is only advisory to the county commission. Supporters say the projects bring jobs, healthy lease payments to land owners who host the turbines and carbon-free electricity.

Oregon’s renewable power standard requires Portland General Electric and PacifiCorp to obtain 25 percent of their energy from new renewable sources by 2025. A more aggressive standard in California has also driven fast-paced wind farm development in Oregon.

Joshi said she’s not sure yet when the health office will complete its work. Updates will be posted at www.oregon.gov/DHS/ph/hia/windenergy.shtml, which also includes details of the sessions on Nov. 3 and 4.

THIRD FEATURE:

PANEL: SPREAD WIND'S REWARDS

MAKE UP FOR LOSSES: Cape Vincent team says property value, tourism are at risk  

October 19, 2010
by Nancy Madsen 

CAPE VINCENT — The town's wind economics committee, finding risks and rewards of wind farm development, has offered bold recommendations to spread rewards around and compensate nonparticipating landowners for any losses they incur.

The committee, which released its report Oct. 7, saw risks to property values, school district aid and tourism. On the other hand, wind power projects would have payments for landowners and for taxing jurisdictions through payment-in-lieu-of-taxes agreements.

The report also briefly pointed to other financial risks, including the failure of the developer to pay agreed payments, the owner terminating operation and the owner not saving enough money for decommissioning costs. The town and residents could incur legal fees from disagreements or disputes.

To limit the possibility of economic harm, the committee recommended that the town:

■ Adopt a zoning law that considers all effects of wind power development.

■ Create a planned development district in the town for turbines.

■ Negotiate PILOT agreements that "fairly and fully compensate" the town.

■ Require compensation to individuals for effects that can't be mitigated.

■ Require property value protection assurance.

■ Require a buyout plan for properties negatively affected.

■ Require bonding to ensure compliance.

■ Establish a reserve fund to cover any town-incurred project costs.

■ Establish a decommissioning plan.

The committee was composed of Assessor Robert V.R. Barnard; Zoning Board of Appeals member Robert S. Brown; Rockne E. Burns, owner of Willow Shores Mobile Home Park and past Planning Board member, and Cyril C. Cullen, past chairman of the Planning Board. Joseph A. Menard, superintendent of Thousand Islands Central School District, advised the committee on school-related issues.

"During this study it has become apparent that the Town and School may well see a financial gain through PILOT payments," the report said. "In addition to the Town and School, participating lease holders, who comprise only 3.9% of the property owners, in the Town are the only citizens that will benefit directly."

The report described the town's land value and compared the participating and nonparticipating land areas.

The total assessed value in the town, including tax-exempt properties, is $310.7 million. Property owned by participating landowners comprises 13,679 acres totaling $9.2 million in assessments. Property owned by nonparticipating landowners comprises 22,267 acres with a value of $301 million. While the participating landowners' property covers 38 percent of the town's area, it includes only 2.9 percent of the assessed value.

Contrary to assertions by St. Lawrence Wind Farm's developer, Acciona Wind Energy USA, in the final environmental impact statement, the report said, "Indications are there will be an overall decrease in property values with the potential for significant negative impact on assessments and related factors such as tax rates and the ability to market property at a fair price."

For example, nonparticipating property owners in the project areas could lose 20 percent to 40 percent of their properties' value, while others within 1,000 feet of turbine sites could lose 15 percent to 25 percent of their value.

One of the effects for lower assessments is the town and school district could raise tax rates to collect the same amount in property taxes, the report said.

On revenue for those in the town, the report recognizes that participating property owners could see more than $4,000 per year per turbine. The town and school district also would receive revenue, but through a payment-in-lieu-of-taxes agreement instead of full property taxes.

"Town income would be whatever the Town negotiates for a PILOT agreement," the report said. "The Town's share of the PILOT agreement could be as much as $8,000 to $8,300 per turbine annually."

The school district's share now is extra income, but that situation could change if the state decides to include it as income.

"Although, there have not been official discussions at the State level that this practice is going to change, it should be noted that school districts across New York State have seen reductions in State Aid and it is possible that at some point PILOT revenues may affect school districts' State Aid," the report said.

If property values decline, the district may see more state aid through the wealth ratio, the report said.

The report also finds that tourism likely would be hurt by wind turbines. Those who come to Cape Vincent to see turbines "may slow down when they first go past a wind turbine, but do not spend any significant amount of time looking at them," it said.

For visitors who come to spend time on the St. Lawrence River and Lake Ontario, turbines "will not help promote the benefits of Cape Vincent that have drawn so many people to our town for decades," the report said. "It is felt that the negative effect of this industrial complex can be moderated by careful placement of the individual turbines so as to minimize their impact on the positive aspects of the town."

ON THE NET

Cape Vincent Wind Economic Impact Committee report:

www.townofcapevincent.com/windcommittee.html

8/13/10 DOUBLE FEATURE: Like a bad neighbor, Acciona is there. And ignoring noise studies AND Wind Farm Strong Arm: Wisconsin looks in the mirror and sees Maine: 

Note from the BPWI Research Nerd: Spanish wind giant, Acciona, owns easements to land in Rock County for a large wind project that would occupy Magnolia Township. The proposal is for 67 wind turbines to be sited in Magnolia's 36 square miles.

Acciona has not responded to repeated email from Better Plan asking for information about the project.

The contracts held by Acciona for farmland in Rock County were solicited by a "local" wind developer, EcoEnergy, who wooed local residents, held contract signing parties and open houses and then quickly 'flipped' the project to Spanish ownership. How much EcoEnergy made by selling the valuable contracts is unknown, but the farmers who signed away their land won't see any of it.

Like a bad neighbor, Acciona of Spain is there.

Acciona submits 'final' statement; Developer ignores consultant's views on noise analysis

SOURCE: Watertown Daily Times, www.watertowndailytimes.com

August 12, 2010

By Nancy Madsen

CAPE VINCENT — The developer of St. Lawrence Wind Farm has eliminated two wind turbines for noise and wetland considerations, but it ignored the conclusions of the town’s consultant on noise analysis in order to maintain a 51-turbine array.

Acciona Wind Energy USA submitted the possible Final Environmental Impact Statement to the town Planning Board on July 28. The board will meet at 7 p.m. Wednesday at the Cape Vincent Recreation Park, 602 S. James St., to decide whether to accept the statement and deem it complete.

The developer’s consultant, David M. Hessler of Hessler Associates Inc., Haymarket, Va., maintained that his handling of noise measurements and analysis were proper. But the town’s independent consultants, Gregory C. Tocci and William J. Elliot of Cavanaugh Tocci Associates, Sudbury, Mass., found fault with the analysis.

Mr. Hessler used sound levels that were an average of 44 decibels during the summer and 37 decibels during the winter when the wind is blowing.

According to a state Department of Environmental Conservation guideline, noise exceeding six decibels above ambient is considered intrusive or objectionable. Hessler Associates’ analysis showed the array of turbines would not create noise above six decibels above ambient at any residence.

“All residences, whether participating or not, lie outside of the 42 dBA sound contour line and will be short of the 6 dBA NYSDEC threshold,” the developer wrote in the statement. “However, wind and weather conditions (i.e., temperature inversion and low level jetstreams) may develop from time to time causing Project sound levels to increase, sometimes substantially, over the normal predicted level.”

Those periods should be short, the statement said, although it noted that the cumulative effects if both St. Lawrence Wind Farm and BP Alternative Energy’s Cape Vincent Wind Farm were built would push noise levels above the DEC guideline. The statement predicted higher levels for six participating and 37 nonparticipating residences.

In letters to town engineer Kris D. Dimmick, of Bernier, Carr & Associates, Watertown, Mr. Elliot and Mr. Tocci repeated criticism of the noise analysis Mr. Elliot described to town officials in February. He said then that Hessler’s data did not statistically support the correlation between wind speed and noise. To get a stronger correlation, the wind speed and noise levels would have to be taken at the same location, but they were not, he said.

In a May 14 letter, the two disputed the background noise levels that Mr. Hessler assumed through his regression analysis. Mr. Elliot and Mr. Tocci had measurements that averaged five decibels below the levels Mr. Hessler predicted in his regression analysis. They recorded the sound levels at specific wind speeds.

If ambient noise levels have been overstated in the impact statement, it will allow higher levels of noise from turbines without violating DEC limits.

“Using a regression to associate background sound with wind speed frequently underestimates wind turbine noise impact by permitting frequent conditions where turbine sound significantly exceeds the NYSDEC margin of 6 dBA,” Mr. Elliot and Mr. Tocci wrote.

In a rebuttal letter June 21, Mr. Hessler said the actual measured noise values were too strict.

“Using these overly conservative values in the various wind speed bins as bases for evaluating the nominal impact threshold of a 6 dBA increase would undoubtedly and unrealistically suggest that adverse noise impacts will occur on a widespread basis over the entire project area and beyond,” Mr. Hessler wrote.

In a July 15 letter, Mr. Elliot and Mr. Tocci again argued against using the regression analysis and for the actual measurements from wintertime.

Using the measurements “leads to an impact threshold based on the NYSDEC policy that is approximately 5 dBA lower than the impact threshold estimated by Hessler” at 13.4 miles per hour, they wrote. “It is at this wind speed that Hessler indicates the greatest potential noise impact may occur.”

They reiterated that the Hessler analysis does not show a “conclusive relationship” between sound and wind speed. As a result of the averages used by Hessler, Cavanaugh Tocci suggested instituting a resolution process for noise complaints.

The developer proposed a complaint resolution procedure. A written complaint from a resident or business would go first to the developer. Acciona would have five days to respond and if the developer couldn’t fix it, the complaint would be sent to a town designee for investigation.

Any testing would begin within 10 days of the report from Acciona. Test results would go to the plaintiff and town within 30 days. If the town Planning Board agreed the turbine violates permit conditions, the developer would mitigate it. If the plaintiff wasn’t happy with the resolution or it had been longer than 30 days and there had been no resolution, an appeal could be made to the complaint resolution board.

The board will have a member from the developer and the town and an independent consultant agreed upon by the developer and town. That member can change depending on the nature of the complaint.

The board has 30 days to hear the complaint and 30 days to render a binding decision.

Repeated complaints will trigger additional investigations only if the town determines the operational characteristics have changed since the first complaint.

The final statement also proposes eliminating two turbines for noise and wetland concerns, moving a turbine 2.9 miles and adjusting 10 turbines to decrease wind turbulence. It includes additional well, wetland and wildlife studies. Five segments of roads and 23 intersections will need improvements to handle the construction, and 31 of the 51 turbines will be lit with simultaneously flashing beacons, according to Federal Aviation Administration standards.

The statement also responds to all comments made by agencies and the public on the draft and supplemental environmental impact statements.

The statement is available at the Cape Vincent Public Library, 157 N. Real St.; Lyme Free Library, 12165 Main St., Chaumont, and Cape Vincent town clerk’s office, 1964 Route 12E. If it is accepted as complete, it will be available on Acciona’s website as well.

If the board deems the statement complete, it can complete its findings and end the environmental review after 10 days. The board has indicated that could happen Sept. 15. Other involved agencies, but not the public, also will weigh in with findings.

SECOND FEATURE:

WIND POWER LAW HASN'T RESOLVED DEVELOPMENT CONFLICTS

 SOURCE: Maine Center For Public Interest Reporting, bangordailynews.com,

 By Naomi Schalit, Senior Reporter

AUGUSTA, Maine — After proposing major changes to state law that would speed up the review of wind power projects, Gov. John Baldacci’s wind power task force members went one step further: They made a map.

Without the map, the law would just be a set of rules. The map was essential because it showed where wind turbines could go to get fast-track consideration.

The map designated all the organized towns and about a third of the unorganized territory as the state’s “expedited wind zone” where that speedy consideration of projects would take place. The task force also proposed to allow the Land Use Regulation Commission to expand the areas if applicants met certain standards.

How that map got drawn is not clear from the official record of the task force’s meetings. That’s because summaries for the last two meetings don’t exist, said task force chair Alec Giffen’s secretary, Rondi Doiron.

“Everyone was working straight out on getting the report done and no one had time to get the summaries done,” Doiron wrote in an email to the Maine Center for Public Interest Reporting.

But Giffen and others freely describe the map’s genesis: First, Giffen consulted with the developers’ representatives one-by-one, as they were loathe to share proprietary information with competitors. Then he went to the environmental groups and asked what areas they wanted to protect.

Then he came up with a proposed map designating expedited wind development areas.

“I integrated, based on what I knew about what areas were important for what kinds of uses, presented it to the task force and got concurrence that the way in which it was outlined made sense,” Giffen said.

Others describe the map-drawing process as a last-minute rush to get the task force’s report done in time for legislators to consider as they neared the end of a short session.

“There was a lot of ‘Here, here, here and here’ and ‘No, no, no and no,” during the map debate, said task force member Rep. Stacey Fitts, R-Pittsfield. “It changed several times.” Maine Audubon’s Jody Jones described the process as “I want this in, I want this out.”

Whatever the process looked and sounded like is lost to the public record because no minutes were taken or recorded.

And that, says Sun Journal managing editor Judy Meyer, who’s also vice president of the Maine Freedom of Information Coalition, is “shocking.”

Maine law doesn’t require groups like the governor’s wind task force to memorialize deliberations, says Meyer.

“There’s no requirement that they record their meetings or produce minutes,” she says. “What smells particularly about this is that there are some summaries and not others. That’s a real eyebrow raiser. You’d think a governor’s task force would have the ability to keep minutes of its proceedings.”

Giffen says the map — which was approved by the full Legislature — is only the first step in deciding whether a project should be built in a specific place.

“It’s a coarse filter to try to get wind power development guided to parts of the landscape where it’s already partially developed and you already have infrastructure,” he said. “Then you have the finer filters of the regulatory process.”

Task force member Pete Didisheim of the Natural Resources Council of Maine, who was one of the group’s strongest proponents of wind power development, says the map provided an essential tool by taking a lot of uncertainty out of the process of siting wind farms. That’s because he says that the designation of expedited zones announced, by implication, where developers shouldn’t go.

“I don’t think that any other state has drawn a map that says to developers, ‘Don’t go here,’” said Didisheim.

Attorney Chip Ahrens, who attended task force meetings on behalf of two clients, a large wind power developer and an installer of small wind turbines in commercial and residential sites, said that approach turned state regulation on its head — appropriately:

“There had always been on the table the state saying where wind power should go,” said Ahrens, who stressed he was not speaking on behalf of his clients. “I said, ‘let’s say where it should not go.’”

And just because a site is in the expedited permit zone doesn’t mean it’s an automatic approval once a wind power project applies for a permit to build.

“The law specifically says that the permitting agency shall not compromise its regulatory review criteria,” says LURC director Catherine Carroll. “It’s not a slam dunk.”

Law tested, angering some

That point was made acutely clear this year in one of the first tests of the new law, an application by TransCanada to build turbines in the expedited wind zone near its western Maine Kibby Mountain project.

At a meeting on July 7 in Bangor, LURC commissioners — all of whom were nominated or renominated by Gov. John Baldacci — indicated by straw vote they’d deny TransCanada’s request to construct the turbines.

Several environmental organizations, including the three groups who were on the governor’s wind power task force, testified against portions of the project. Objections ranged from damage to wildlife to degradation of the scenically valuable high mountain site. Many of the commissioners likewise expressed concerns about the potential harm the project would do to the site.

Commissioners struggled to weigh the new law’s goals for wind power development against the environmental problems posed by the project.

“I’m terribly conflicted here,” said Commissioner Steve Schaefer.

He and other commissioners said they were unclear whether the law’s goals for wind power were binding on them and would force them to approve a project they didn’t feel protected the landscape they were legally obligated to protect.

“The Wind Power Act looms large here,” said Commissioner Ed Laverty.

“We’re all going to reduce global warming and our carbon footprint,” continued Laverty, “but most of the immediate benefits of projects like these do not accrue to the people of Maine, they’re exported through the grid elsewhere.

“What stays with us in the state of Maine are the environmental impacts.”

A few days after the LURC meeting, TransCanada’s project manager Nick DiDomenico was outraged at the meeting’s outcome. The environmental groups that had participated in the task force and then opposed TransCanada’s proposal drew his special wrath:

“The [environmental groups] were at the table when the map was drawn up,” he said. “That to me means these areas are acceptable for visual impacts. Maybe we were a little naive in drawing that conclusion.

“We thought the Wind Power Act meant something.”

Within eight days, construction company Cianbro’s chairman Peter Vigue had published a column in the Bangor Daily News criticizing LURC. Cianbro has done construction work on TransCanada’s wind power projects as well as others in the state.

“This unpredictable regulatory environment will discourage investment in Maine,” wrote Vigue.

On Aug. 1, retired law professor Orlando Delogu published a similarly sharp-toned column in the Maine Sunday Telegram.

“Reading a transcript of the recent LURC hearing on TransCanada’s proposed Kibby No. 2 wind energy project, a 45-megawatt expansion of an existing facility in Chain of Ponds Township, makes you want to cry for Maine’s economy and energy future,” wrote Delogu.

“And then it makes you mad.”

But state Sen. Peter Mills isn’t mad at LURC. Instead, he calls the LURC commissioners “victims” of a new state policy that isn’t clear enough about if, and how, competing values can be resolved.

“No one wanted to be bothered with the details,” said Mills. “We’ll just leave it up to LURC to figure out what we mean. We passed this thing, but we never gave them the tools to deal with this.”

LURC Commissioner Sally Farrand mirrored Mills’ frustration, when she remarked during the July 7 hearing, “Boy, I sure hope we can tighten up some of this stuff because I see it as a skating rink with some very dull skates.”

Other problems

There are other problems created by the legislation. One unintended consequence is that Maine mountain ridgelines, once available at relatively cheap prices to those who wanted to preserve them, have become coveted – and expensive – pieces of land.

“Were it not for the wind-power market, alpine land has fairly limited value,” said Alan Stearns, deputy director of the Bureau of Parks and Lands. “Right now the mathematics is land with wind power potential is not for sale for conservation.

“As long as the market for wind power is dynamic,” said Stearns, “most landowners with wind-power potential are working with wind power developers, not conservation groups, for that land.”

And turbine noise that irritates neighbors has proven to be especially problematic, with residents who live near towers complaining of sleep disturbance and other health problems.

But a comparison of the task force’s report with the governor’s legislation that became the Wind Power Act reveals a significant omission: The recommendation that the environmental protection commissioner be given the power to modify the noise aspects of a project’s permit never made it into the legislation.

Gov. Baldacci supplied the following answer in writing when asked why that provision had been left out of his wind power legislation:

“I relied on the Task Force members’ review of the draft legislation as a complete and accurate reflection of all the recommendations in their Report. If one or more of their recommendations was not included, I was not aware of that nor was any omission or deletion done at my request or direction.”

Task Force Chairman Giffen likewise had no idea how the omission occurred, and told the Center he knew of no plans to correct it.

Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.

“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine — oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines — that’s when I begin to think that the goal is a little farfetched.”

Uncertain future

What’s significant for the state’s wind power policy is that Mills, who wasn’t on the task force, isn’t the only one who now doubts whether the state can — or should — meet the goals promoted by the governor and enshrined in his Wind Energy Act.

Members of Baldacci’s hand-picked task force are dubious as well about whether there really are enough suitable — and politically acceptable — sites to build turbines to meet the goal of 2,000 megawatts by 2015 and 3,000 megawatts by 2020.

“We have to look at whether we have the land base to meet them,” said Jones.

Reaching 3,000 megawatts “is dependent on whether the political consensus holds up,” said task force member and DEP Commissioner David Littell.

“I think it’s a stretch to reach 2,000 by 2015,” said the NRCM’s Pete Didisheim.

But Giffen said he still believes that promoting wind power is an essential response to global warming.

“So big picture here, the way that I look at this, is to say, the idea that there’s not going to be any change in the state of Maine as regards our natural resources or how we generate energy, that’s not a possibility,” said Giffen.

”If we don’t do anyting, we’re going to see massive changes just in our natural resources. The changing climate conditions are going to mean that in 100 years the area around Portland is going to be suitable for loblolly pine (a southern tree species). What does that mean for our existing soils, our existing ecosystems?

“Is no change something that is even possible?” asks Giffen. “No, it’s not. Do we have significant problems with our energy supply and dependence on fossil fuels in terms of climate change? Yes.

“So is Maine well served by having looked at its regulatory system to see how it can deal in a rational way with this kind of development? Is it perfect? I doubt it. Will we learn as we go along? Yes.”

LURC Commissioner Laverty takes another perspective:

“I think we need to take into consideration, there aren’t a lot of these 2,700 plus foot mountains in the state of Maine … I think that we have to pay special attention to the impact on significant resources in these areas, because,” he said, “once you invade these resources, the chances of re-establishing them over time, at least in our lifetimes, probably are fairly slim.”

In the end, the law that was supposed to put conflict to rest has not, and for a host of reasons, both procedural and substantive. Harvard University professor Henry Lee, who teaches energy and international development at the Kennedy School of Government, said the conflict in values that wasn’t resolved by Maine’s Wind Energy Act — where those who want to act against the threats of global warming fight land conservationists — is one that’s playing out across the nation and globe.

“I think that this pits to some extent environmental organizations against each other,” said Lee. “Some are focused on pollution issues and see wind and solar and other renewables as a significant improvement in terms of reduced pollution — and it is.

“On the other hand if you’re worried about land use, in a world where … you have a finite quantity of land, there will continue to be significant disputes,” said Lee. “Wind sites tend to be slightly better along the coast and at higher altitudes, exactly where you have sign conflicts with esthetics.

“These disputes are going to get more intense, not less,” Lee said.

7/5/10 The headache Down Under: Like a bad neighbor, Acciona is there AND Wind siting council meeting on Tuesday

Noel Dean has a farm at Waubra but he and his family moved out 13 months ago when their headaches worsened.

“Sore ears, pain in and around the eyes, pain on top of the head, pain in the back of the head, behind the ears and early this year, we started to get throbbing pain at the back of the head and tinnitus,” he said.

“We couldn’t stay there another night – it was that bad.” 

RESIDENTS REJECT WIND FARM HEALTH FINDINGS

SOURCE: ABC News, www.abc.net.au July 5 2010

By Kellie Lazzaro,

Campaigners against wind farms have rejected a report finding no scientific evidence to link wind turbines to health problems.

The National Health and Medical Research Council, which advises the Federal Government, found that there was no evidence that the turbines’ low frequency noise or shadow flicker made people sick.

But residents of Waubra in Victoria’s south-west who live near the state’s largest wind farm, say they are sick and are convinced that wind turbines are to blame.

Noel Dean has a farm at Waubra but he and his family moved out 13 months ago when their headaches worsened.

“Sore ears, pain in and around the eyes, pain on top of the head, pain in the back of the head, behind the ears and early this year, we started to get throbbing pain at the back of the head and tinnitus,” he said.

“We couldn’t stay there another night – it was that bad.”

Mr Dean first complained to the Waubra wind farm operator Acciona in May last year, but the company refused to give him access to the outcome of its investigation.

He then commissioned an independent report into noise levels at his property at a cost of more than $40,000.

He has just received that report by Noise Measurement Services and says it confirms there is a link between the low frequency noise from wind farms and adverse health effects.

“Anything from 1 to 20 hertz can cause adverse health effects and that is what we have found in a pulsing motion. It is a pulsing motion that makes the effects just a lot worse,” he said.

But in a rapid review of existing studies, the National Health and Medical Research Council (NHMRC) has found there is no published evidence of direct pathological effects from wind farms.

The director of the council’s evidence and advice branch, Professor John McCallum, says they have brought together opinion and evidence from all around the world.

“Shadow flicker is the flicking on and off of wind turbine shadows as the blades rotate. It is the glint off the surface of the blades and those are now minimised by treatment of the blades that prevents reflective glint as well, and they are the kind of four main areas that people talk about health effects from,” he said.

He says World Health Organisation (WHO) studies have found no reliable evidence that sound below the hearing threshold will produce physiological or psychological effects.

The NHMRC report refers to a study of three wind farms in the UK that found if people are worried about their health, they may become anxious and suffer stress-related illnesses.

For this reason Professor John McCallum says people who believe they are experiencing health problems should consult a GP, but he says the report commissioned by Noel Dean about noise levels on his farm would need to be further tested.

Donald Thomas also lives at Waubra and was a big supporter of the wind farm, until he too started getting headaches, heart palpitations and high blood pressure.

“We’ve invited the Health Minister and top health officials to actually come out to Waubra to talk to us and see what the problem is first hand, but none of them have bothered to do that. They just look at overseas studies and pick the ones that suit them,” he said.

The National Health and Medical Research Council acknowledges the health effects of renewable energy generation have not been assessed to the same extent as those from traditional sources and recommends authorities continue to monitor research.

The National Environment Protection and Heritage Council has met in Darwin today to consider national wind farm development guidelines.

NOTE FROM THE BPWI RESEARCH NERD: Acciona has several projects in the works in Wisconsin, but we've had no luck getting them to tell us what their plans are for our communities.

 

 

 

WIND SITING HEARING NOTICE

Tuesday  July 6, 2010, beginning at 1:00 p.m and 6:00 p.m.

Docket 1-AC-231

Public Service Commission of Wisconsin
First Floor, Amnicon Falls Room
610 North Whitney Way, Madison, Wisconsin

 [Click here for map]

Audio and video of the meeting will be broadcast from the PSC Website beginning at 1:00.

CLICK HERE to visit the PSC website, click on the button on the left that says "Live Broadcast". Sometimes the meetings don't begin right on time. The broadcasts begin when the meetings do so keep checking back if you don't hear anything at the appointed start time.

 

MEETING NOTICE
Wind Siting Council
Docket 1-AC-231

Agenda

1) Welcome/Review of today’s agenda
2) Review and adoption of meeting minutes of June 21, 2010 & June 23, 2010
3) Straw proposal amendment ballot results
4) Straw proposal revisions based on ballot results
5) Additional revisions to straw proposal prior to end of public comment period
6) Next steps/Discussion of next meeting’s time, place and agenda
7) Adjourn

NOTE FROM THE BPWI RESEARCH NERD:

CLICK HERE TO DOWNLOAD A COPY OF THE WIND SITING COUNCIL STRAW PROPOSAL