8/28/10 TRIPLE FEATURE: Wisconsin Department of Health ignores complaints from state wind project residents, says there are no health issues: What part of "Can't sleep" don't you understand? ---And----AWEA vs DoD + FAA ----AND- The wind devil is in the details: so don't look at the details

Click on the image below to hear what wind siting council member Larry Wunsch has been living with for the past two years. This turbine is located 1100 feet from his home.

STATE OFFICIAL TAKES WIND OUT OF TURBINE HEALTH ISSUE

SOURCE: Green Bay Press-Gazette, www.greenbaypressgazette.com

August 28, 2010

By Tony Walter

A key state health official has notified the attorney for a Brown County citizens group that there isn’t sufficient evidence to show that wind turbines have a negative effect on human health.

To that, attorney Ed Marion replied, “There’s no question in my mind that there’s such a rush to build wind turbines that policymakers are simply ignoring all the evidence against building them. People who dismiss wind turbine complaints are flat wrong.”

Marion, former Gov. Tommy Thompson’s chief of staff, represents the Brown County Citizens for Responsible Wind Energy, a group that opposes a plan by Chicago-based Invenergy LLC to construct a wind farm of 100 turbines in the towns of Morrison, Holland, Wrightstown and Glenmore.

Seth Foldy, state health officer and administrator for the state’s Division of Public Health, said his conclusion is based on a study of scientific evidence.

The citizens group claims considerable evidence shows wind turbines can cause a variety of health problems for nearby residents, including sleep disturbance and headaches.

The PSC-appointed wind siting council has sent proposed turbine rules to the PSC, which is expected to vote on the rules next week. The major issues are decibel limits and setback restrictions.

“Our review of the scientific literature concludes that exposure levels measured from contemporary wind turbines at current setback distances do not reach those associated with objective physical conditions, such as hearing loss, high blood pressure, or flicker-induced epilepsy,” Foldy wrote in a July 19 letter to Marion.

“From this, we conclude that current scientific evidence is not sufficient to support a conclusion that contemporary wind turbines cause adverse health outcomes in those living at distances consistent with current draft rules being considered by the Public Service Commission.”

Marion said he sent three letters to Foldy before receiving a reply and said additional studies have been completed since Foldy’s July 19 letter.

“Washington University in St. Louis, a prestigious institution, released a study this month that said there’s an urgent need to do more research on wind turbine effect,” Marion said.

Marion’s May 13 letter to Foldy cited five studies that he said concluded that wind turbine noise can cause health problems.

“Wind energy proponents claim that it has not been proven that wind turbine noise causes adverse health impacts,” Marion wrote. “More to the point, it has not been proven that wind turbine noise does not cause adverse health effects.”

He called on the state Division of Public Health to conduct more in-depth research on the issue.

Foldy wrote that symptoms such as sleep disturbance and headaches are common and caused by “a wide variety of conditions.

For example, sleep disturbance is a common problem in the general population and may be a sign of an underlying medical disorder. The same is true for symptoms like nausea, headache, problems with equilibrium.”

He said the department’s staff reviewed the five reports that Marion mentioned, as well as more than 150 reports on wind turbines and health. He said the department will continue to review evidence as it becomes available.

Barnaby Dinges, spokesman for Invenergy, said the company “has no comment on the letters between Marion and the state since it was not part of the exchange. It’s really a dialogue between those two parties.”

Invenergy is expected to resubmit its application for the wind farm after the siting rules are approved.

Second feature:

Wind power fights two powerful foes

SOURCE UPI, www.upi.com

August 27 2010

The push for greener energy sources has run into a sizable roadblock with U.S. aviation experts opposing wind turbine construction, a trade group said.

The American Wind Energy Association said a survey of its members found scores of projects in 2009 ran into interference from the U.S. Defense Department and the Federal Aviation Administration, despite a push from the U.S. Energy Department to produce energy from renewable sources, The New York Times reported Friday.

Wind turbines, some of them 400 feet tall, reportedly confuse air traffic controllers, as they resemble storms on weather radar systems. They can also cause planes in some spaces to drop off radar screens entirely, the Times reported.

Dorothy Robyn, deputy undersecretary of defense recently testified that wind turbines create a high risk for planes and compromise national security.

Gary Seifert, a researcher with the Energy Department, called the collision course between Defense Department interests and energy needs “the train wreck of the 2000s.”

“The train wreck is the competing resources for two national needs: energy security and national security,” he said.

The wind energy group said the Defense Department and the FAA stalled or stopped 9,000 megawatts worth of projects in 2009, equal to the amount of wind energy projects constructed during the year.

Wind energy gets huge subsidies. So where are the CO2 reductions?

Source: Energy Tribune, www.energytribune.com

August 27, 2010

By Robert Bryce,

Ed. note: This story is an extended version of an article that appeared in the Wall Street Journal on August 24.

Over the last few years, the wind industry has achieved remarkable growth largely due to the industry’s claim that using more wind energy will result in major reductions in carbon dioxide emissions. There’s just one problem with that claim: it’s not true. Recent studies show that wind-generated electricity may not result in any reduction in carbon emissions, or those reductions will be so small as to be almost meaningless.

This issue is especially important now that states, even in the absence of federal legislation, are mandating that utilities produce arbitrary amounts of their electricity from renewable sources. By 2020, for example, California will require utilities to obtain 33% of their electricity from renewables. About 30 states including Connecticut, Minnesota, and Hawaii, are requiring major increases in the production of renewable electricity over the coming years. Wind, not solar or geothermal sources, must provide most of this electricity, because it is the only renewable source that can rapidly scale up to meet the requirements of the mandate. But those mandates will mean billions more in taxpayer subsidies for the wind industry and result in higher electricity costs for consumers.

There are two reasons wind can’t make major cuts in carbon emissions. The wind blows only intermittently and variably; and wind-generated electricity largely displaces power produced by natural gas-fired generators rather than that coming from plants that burn more carbon-intensive coal.

Because the wind is not dependable, electric utilities must either keep their conventional power plants running all the time (much like “spinning reserve” in industry parlance) to make sure the lights don’t go dark, or they must continually ramp up and down the output from conventional coal- or gas-fired generators (“cycling”).

Coal-fired and gas-fired generators are designed to run continuously. If they don’t, fuel consumption, and emissions of key air pollutants, generally increases. A car analogy helps explain the reason: An automobile that operates at a constant speed — say, 55 miles per hour — will have better fuel efficiency, and emit less pollution per mile traveled, than one that is stuck in stop-and-go traffic. But the wind, by its very nature, is stop-and-go. The result: minimal or no reductions in carbon emissions by shifting conventional generation to wind.

In 2008, a British energy consultant, James Oswald, along with two co-authors, published a study in the journal Energy Policy, which said that any reductions in Britain’s carbon dioxide emissions due to added wind generation capacity “will be less than expected.” The study went on to say that neither the extra costs of cycling the power plants “nor the increased carbon production are being taken into account in the government figures for wind power.”

An April study by Bentek Energy, a Colorado-based energy analytics firm, looked at power plant records in Colorado and Texas. (It was commissioned by the Independent Petroleum Association of the Mountain States.) Bentek concluded that despite huge investments, wind-generated electricity “has had minimal, if any, impact on carbon dioxide” emissions. Thanks to the cycling of Colorado’s coal-fired plants in 2009, for example, at least 94,000 more pounds of carbon dioxide were generated because of the repeated cycling. In Texas, Bentek estimated that the cycling of power plants due to increased use of wind energy resulted in a slight savings of carbon dioxide (about 600 tons) in 2008 and a slight increase (of about 1,000 tons) in 2009.

This month, the US Association for Energy Economics published a paper by Ross Baldick, a professor of electrical and computer engineering at the University of Texas at Austin, which concluded that new wind generation capacity “may not be decreasing greenhouse emissions. However, even assuming that wind displaces fossil emissions, it is not ‘worthwhile’ for reducing greenhouse emissions” even if regulators put a price on carbon dioxide of up to $35 per ton.

The problems posed by the intermittency and variability of wind energy could quickly be cured if only we had an ultra-cheap method of storing large quantities of energy. If only. The problem of large-scale energy storage has bedeviled inventors for centuries. Alessandro Volta and Thomas Edison both produced working batteries. Edison spent years working on battery technology, sinking about $30 million of his own money (in current dollars) into his quest for a durable, high-capacity battery. He had some success. But modern batteries have the same suite of problems that Edison faced: they are too big, too expensive, too finicky, and lack durability.

Other solutions for energy storage like compressed air energy storage and pumped water storage are viable, but like batteries, those technologies are expensive. And even if the cost of energy storage falls dramatically — thereby making wind energy truly viable — who will pay for it? Further, even if we have a dramatic breakthrough in energy storage, the deployment of that new technology will likely take decades.

Despite the lack of storage, the US and other countries continue to deploy huge amounts of new wind generation capacity and that expense is being undertaken with the assumption that wind energy will lower carbon dioxide emissions. But federal authorities have done some estimates on how more wind energy will affect emissions. And those estimates are revealing.

Last year, the Energy Information Administration estimated the potential savings from a proposed nationwide 25% renewable electricity standard, a goal that was included in the Waxman-Market energy bill which narrowly passed the US House last year. In its best-case scenario, the annual carbon dioxide savings from that mandate would be about 306 million tons by 2030. Given that the EIA expects annual US carbon dioxide emissions to be about 6.2 billion tons in 2030, that expected reduction will only equal about 4.9% of US emissions. That’s not much when you consider that the Obama administration wants to cut US carbon dioxide emissions by 80% by 2050.

Earlier this year, another arm of the Department of Energy, the National Renewable Energy Laboratory, released a report whose conclusions were remarkably similar to those of the EIA. This report focused on integrating wind energy into the electric grid in the eastern US, which has about two-thirds of all US electric load. If wind energy were to meet 20% of electric needs in the eastern US by 2024, according to the report, the likely reduction in carbon emissions would be less than 200 million tons per year. (All the scenarios in the NREL analysis cost a minimum of $140 billion to implement and the issue of cycling conventional power plants is only mentioned in passing.)

Coal emits about twice as much carbon dioxide during combustion as natural gas. But wind generation mostly displaces natural gas because natural gas-fired generators are often the most costly form of conventional electricity production. That said, if regulators are truly concerned about carbon emissions (and cutting air pollution) they should be encouraging gas-fired generation at the expense of coal. And they should be doing so because drillers are unlocking galaxies of natural gas from shale beds, so much so that US natural gas resources are now likely large enough to meet all of America’s natural gas needs for a century.

Meanwhile, the wind industry is pocketing subsidies that dwarf those garnered by the oil and gas sector. The federal government provides a production tax credit of $0.022 for each kilowatt-hour of electricity produced by wind. That amounts to $6.44 per million BTU of energy produced. Meanwhile, a 2008 EIA report said subsidies to the oil and gas sector totaled $1.9 billion per year, or about $0.03 per million BTU of energy produced. Thus, on a raw, per-unit-of-energy-produced basis, subsidies to the wind sector are more than 200 times as great as those given to the oil and gas sector.

Kevin Forbes, the director of the Center for the Study of Energy and Environmental Stewardship at Catholic University, told me that “Wind energy gives people a nice warm fuzzy feeling that we’re taking action on climate change.” But when it comes to carbon dioxide emissions, “the reality is that it’s not doing much of anything.”



2/9/10 TRIPLE FEATURE: Dude, Where's My Wind Farm Stimulus Money? AND When an 'empty gesture' is full of meaning: Town of Holland's wind moratiorium and what the PSC says about it, AND What's that smell? Is it the conflict-of-interest problem in Brown County?

New Wind Farms in the U.S. Do Not Bring Jobs

Millions have been invested in wind farms, but it hasn't brought jobs

 Click Here for Source: ABC World News 

Jonathan Karl

Feb. 9, 2010

 Despite all the talk of green jobs, the overwhelming majority of stimulus money spent on wind power has gone to foreign companies, according to a new report by the Investigative Reporting Workshop at the American University's School of Communication in Washington, D.C.

Nearly $2 billion in money from the American Recovery and Reinvestment Act has been spent on wind power, funding the creation of enough new wind farms to power 2.4 million homes over the past year. But the study found that nearly 80 percent of that money has gone to foreign manufacturers of wind turbines.

 So Where Are the Jobs?

"Most of the jobs are going overseas," said Russ Choma at the Investigative Reporting Workshop. He analyzed which foreign firms had accepted the most stimulus money. "According to our estimates, about 6,000 jobs have been created overseas, and maybe a couple hundred have been created in the U.S."

Even with the infusion of so much stimulus money, a recent report by American Wind Energy Association showed a drop in U.S. wind manufacturing jobs last year.

Sen. Chuck Schumer, D-N.Y., called the flow of money to foreign companies an outrage, because the stimulus, he said, was intended to create jobs inside the United States.

"This is one of those stories in Washington that when you tell people five miles outside the Beltway, or anywhere else in America, they cannot believe it," Schumer told ABC News, "It makes people lose faith in government, and it frankly infuriates me."

Matt Rogers, the senior adviser to the Secretary of Energy for the Recovery Act, denied there was a problem.

"The recovery act is creating jobs in the U.S. for American workers," said Rogers, "That is what the recovery act is about, that is what it is doing. Every dollar from the recovery act is going to create jobs for the American workers here in the U.S."

How Did This Happen?

Several of the large European turbine manufacturers had limited manufacturing facilities in the United States, but there was nothing in the stimulus plan that required that the turbines, or any other equipment needed for the wind farms, be made here, said Rogers. There are strict "Buy America" provisions in the Recovery Act, but this Green Energy Stimulus initiative turned the existing tax credits into cash grants, bypassing the "Buy America" provision.

Iberdrola, one of the largest operators of renewable energy worldwide, is based in Spain and has received the most U.S. stimulus dollars -- $577 million. It buys some of its turbines from another Spanish manufacturer, Gamesa, which has a U.S. connection. Gamesa has two facilities to manufacture turbine blades in Pennsylvania, but the company said the market forced it to temporarily lay off nearly 100 workers.

Eric Sheesley was one of those laid off from the Gamesa plant before Thanksgiving. "When we're employing other countries, we can't feed our kids at home. It gets hard you know." Sheesley had a glimmer of hope when a letter arrived this week telling him to report back to work next week.

One reason so much money is going overseas is that there is not much of a wind power industry in the United States -- only two major American manufacturers make wind turbines: General Electric Energy and Clipper Wind based in Carpinteria, Calif. Even those companies do a significant amount of their manufacturing overseas. General Electric told ABC News that GE's Renewable Energy business has 3,000 employees around the world, 1,350 here in the United States.

Schumer said the way to revitalize the domestic wind power industry and to create green jobs is to require that at least some of the turbine equipment to be made in the United States.

An American Farm With Chinese Jobs

Perhaps the most controversial wind project is one that has yet to receive stimulus money.

A Chinese company called A-power is helping to build a massive $1.5 billion wind farm in West Texas. The consortium behind the project expects to get $450 million in stimulus money.

Walt Hornaday, an American partner on the project, said it would create some American jobs. "Our estimation," he said, "is that we are going to have on the order of 300 construction jobs just within the fence of the project."

But that's in addition to 2,000 manufacturing jobs -- many of them in China.

Lauren Reynolds, a reporter at ABC's San Diego affiliate 10 News, paid a visit to the vacant office of A-power.

To read more about how wind energy companies in San Diego are forced to spend their federal stimulus dollars abroad, go to today's San Diego Tribune and the Watch Dog Institute's Web page.

Second Feature:

Holland backs hollow wind farm moratorium

If the town wants a moratorium, the state has no reason to disagree, said PSC spokeswoman Teresa Weidemann-Smith.

“It’s the community’s right to make those decisions,” she said. “But ultimately, the decision by the PSC will take precedence.”

Source: Daily Reporter

By Paul Snyder

February 9, 2010

Local solidarity is driving a Holland wind farm moratorium that has no chance of success if the Public Service Commission of Wisconsin approves a project in the town.

“We know the PSC will have final say in this project,” said Holland Supervisor Michael Geiger. “We’re just letting them know how we feel about it. When it comes to town politics, we’re about as grass roots as you get.

“The people that live next door want to know you’re supporting them. That’s what I’m doing.”

Holland is one of four Brown County towns targeted by Chicago-based Invenergy LLC for the estimated 100-turbine Ledge Wind Farm. If the project advances, Geiger said, Invenergy could build 22 turbines in Holland.

But the town has enacted a one-year moratorium on wind farm development and revised its setback standards for turbines from 1,000 feet to a half-mile from buildings.

Invenergy representatives did not return calls for comment.

If the town wants a moratorium, the state has no reason to disagree, said PSC spokeswoman Teresa Weidemann-Smith.

“It’s the community’s right to make those decisions,” she said. “But ultimately, the decision by the PSC will take precedence.”

The PSC has authority over projects expected to generate more than 100 megawatts of electricity. Weidemann-Smith said the Ledge project is expected to generate 150 megawatts.

According to state law, if the PSC approves a project, it can proceed despite any local ordinance prohibiting the project.

The PSC has not yet begun its review of the Ledge Wind Farm proposal, Weidemann-Smith said, because Invenergy has not submitted a complete proposal for the project. She said she does not know when that will happen.

Once the PSC begins its formal review of the project, she said, there will be plenty of time for local comments.

The comments are coming in already. The PSC has an open docket on the project with more than 80 public comments.

Jon Morehouse, a member of the executive committee for Brown County Citizens for Responsible Wind Energy, said waiting until the public comment period to speak out against the project would not send as strong a message.

“The moratorium is something that was voted on and publicized,” he said. “If you say nothing, you get run over.”

The Brown County citizens group encouraged the town to enact the moratorium, Geiger said, and the other towns in line to host Ledge turbines also are being encouraged to enact moratoriums. He said he knows the moratorium means nothing if the PSC approves the project, but an empty gesture is better than no gesture.

“The residents at the last two meetings have said they’re prepared to fight,” he said. “I don’t know how they’ll do that, and I don’t really want to know. All I know is with the moratorium, I’m doing something the majority wants.

“If you don’t do something they want, they’ll get somebody who will.”

VISIT THE DAILY REPORTER’S SPECIAL WIND FARM PROJECT PROFILE PAGE

THIRD FEATURE:

Wind farms causing conflict-of-interest controversies among Brown County town boards

As Brown County pursues wind farm bans, some of their officials have already signed contracts for turbines

SOURCE Greenbay Press-Gazette

February 10, 2010

By Scott Williams

As residents seek help stalling a wind farm development in southern Brown County, some local officials are facing conflict-of-interest questions because they have signed deals with the developer allowing wind turbines on their property.

The issue has ensnared town board members in Morrison and Wrightstown, and it is slowing action on wind farm opponents' efforts to delay the development.

Morrison Town Board members on Tuesday postponed action on a proposed wind farm ban because they are awaiting legal opinions on whether Trustees Kevin Collins and Ron Lemke should participate in the decision.

Collins and Lemke both have signed contracts with Invenergy LLC, the Chicago-based developer that wants to build Brown County's first major commercial wind farm. The developer has offered about $8,000 a year to landowners willing to permit a 400-foot wind turbine on their property.

Morrison Town Chairman Todd Christensen said he would not allow the board to discuss the wind farm until determining whether Collins or Lemke has a conflict.

"We're stepping very carefully here," Christensen said. "I just don't want to put anybody in any situation where they're going to get into trouble."

The same predicament faces Wrightstown Town Chairman William Verbeten and Trustee Ronald Diny, both of whom have signed contracts with Invenergy.

With a vote scheduled tonight in Wrightstown on a proposed moratorium on wind farm construction, Verbeten said he might abstain from the vote or postpone action entirely.

Verbeten said Tuesday that he signed a deal allowing a wind turbine on his property before he realized the Town Board would play a role in the development. The final decision on large commercial wind farms in Wisconsin normally comes from the state Public Service Commission.

"We weren't going to be involved," Verbeten said. "We were out of it."

But an opposition group known as Brown County Citizens for Responsible Wind Energy is pushing local elected officials to impose moratoriums or take other action to derail the project.

State law prohibits elected officials from participating in any official issue in which they have a substantial financial interest.

Reid Magney, spokesman for the state Government Accountability Board, said the law does not define substantial financial interest, but state officials interpret it to mean anything more than token.

"We would expect local elected officials — and companies doing business in Wisconsin — to know the law and not put local elected officials in jeopardy," Magney said.

Invenergy is seeking state approval to build 100 wind turbines in southern Brown County, including 54 in Morrison and 20 in Wrightstown. The rest would be built in the towns of Holland and Glenmore, although Holland Town Board members last week approved a one-year moratorium.

Invenergy contends that such local roadblocks are meaningless because state regulators can override all such obstacles when they decide whether to permit the project.

Company vice president Joe Condo said town trustees in Brown County perhaps should abstain from official decisions if those trustees have signed contracts to participate in the development. But considering that the state has the final say, Condo added, "It's really a moot point."

An attorney advising Morrison officials has outlined other ways that the town could involve itself, including passing a resolution on the wind farm proposal or intervening in the state regulatory case.

Steven Gillis, the town of Wrightstown attorney, said he does not perceive a conflict for Verbeten or Diny, at least not on the moratorium issue scheduled to be discussed tonight.

Gillis said he still must conduct more research to determine if the trustees could participate in other issues related to the project, including a local conditional use permit that he believes will be required for the wind farm.

"We'll cross that bridge when we come to it," he said.

Diny and Lemke could not be reached for comment.

Collins declined to discuss his Invenergy contract except to say that although he sees no conflict, he would abstain from any Town Board vote if necessary.

Asked how a three-member board could decide an issue without two members participating, Collins said, "I'm not sure how they'll address that."