3/26/10 DOUBLE FEATURE: We Energies picks builders for Glacier Hills AND First Open Meeting of Wind Siting Council Monday, March 29, 2010 AND today's homework assignment

Butler Ridge Wind Farm in Dodge County

We Energies picks builders for Glacier Hills
 

SOURCE: The Daily Reporter

March 25, 2010

We Energies has selected The Boldt Co., Appleton; Michels Corp., Brownsville; and Edgerton Contractors Inc., Oak Creek, to build the Glacier Hills Wind Park in Columbia County. (Photo by Joe Yovino)

We Energies has selected three Wisconsin contractors to build the Glacier Hills Wind Park.

The three contractors are The Boldt Co., Appleton; Michels Corp., Brownsville; and Edgerton Contractors Inc., Oak Creek. The project to build a wind farm in Columbia County is scheduled to begin in May or June.

VISIT THE DAILY REPORTER’S PROJECT PROFILE PAGE ON THE GLACIER HILLS WIND PARK <http://dailyreporter.com/glacier-hills-wind-park/>

The project’s construction budget will be between $335 million and $413.5 million, depending on which type of turbines is used and the number of turbines in the farm, said We Energies spokesman Brian Manthey.

In April, the utility will nail down the number of turbines and their locations, he said.

SECOND FEATURE

SOURCE: Public Service Commission

Docket # 1-AC-231

MEETING NOTICE

Wind Siting Council 1-AC-231

Public Service Commission of Wisconsin
Pecatonica River Conference Room (Lower Floor)
Public Service Commission Building
610 North Whitney Way, Madison, Wisconsin

[Click here for map]

Monday, March 29, 2010, beginning at 9:00 a.m.

Agenda

1) Greetings:

 Overview of process and expectations, time line

 Introduction of Commission staff working with Council

 Open meeting requirements

 Administration of Oath

2) Self-introductions by members of Wind Siting Council

3) Election of officers: Chair, Vice-Chair, and Secretary

4) Administrative:

 Reimbursement of expenses

 Schedule of Future Meetings

 Designated substitutes

 Instructions regarding use/enrolling in Electronic Regulatory Filing System (ERF)

 Overview of rule-making process and additional Act 40 requirements

5) Review of Draft Rules Outline/topics

 Explain how developed

 Topics/items that are unclear

 Topics/items not in outline which council recommends for inclusion

6) Discussion of how to proceed with future work

7) Next steps/Adjourn

This meeting is open to the public.

If you have any questions or need special accommodations, please contact Deborah Erwin at the Public Service Commission of Wisconsin by telephone at (608) 266-3905 or via e-mail at deborah.erwin@wisconsin.gov.

 

NOTE FROM THE BPWI RESEARCH NERD:

Do Your Homework:

Visit the PSC docket for the siting council frequently to see the latest posts, and add comments of your own for PSC staff members to read and consider as they prepare summaries for the Commissioners.

If you want to be sure your comments are read by the commissioners themselves you'll have post your comments again during the later hearing phase so they will be considered testimony.  

Visit the siting council docket by CLICKING HERE to get to the PSC website In the box that says "Link Directly to a Case", type in this docket number 1-AC-231

REQUIRED READING:

For those who are following the creation of the PSC siting guidelines, we'll be posting a series of documents and news stories for review.

Officials cover up wind farm noise report

by Jonathan Leake and Harry Byford 
December 13, 2009

Want more? CLICK HERE to read Today's 'Wind Turbines in the News' 

OR on the links below to read the stories at their source

3/25/10 Ice, big winds hobble wind farm

SOURCE: Nova Scotia News- The Chronicle Herald

"Extreme winds, along with cold temperatures and a buildup of ice, crashed three test towers and halted power production at RMSenergy’s wind farm in Pictou County, said company president Reuben Burge in an interview in Halifax on Wednesday.

The heavy ice conditions stopped the blades from turning, resulting in a 20 per cent loss of production in January and February, he said.

 

Disease and wind turbines menace bat populations

SOURCE: Orangeville Citizen, Ontario

" A University of Calgary bat mortality study, conducted between 2006 and 2008, determined that the vast majority of bats found dead below turbines near Pincher Creek, Alberta, suffered severe injuries to their respiratory systems consistent with a sudden drop in air pressure – called barotrauma – that occurred when the animals got close to turbine blades.

The study showed that 90 per cent of the bats examined after death showed signs of internal hemorrhaging consistent with barotraumas, while only about half of the bats showed any evidence of direct contact with the blades."

CLICK HERE TO READ THE WHOLE STORY




3/18/10 TRIPLE FEATURE: How they picked them, we don't know: Meet the PSC's new Wind Siting Council AND What the new rules may mean for Brown County AND What did the wind developer say to 1000 people in a bad mood?

WE Energies Blue Sky/ Green Field project in Fond du Lac County, WIsconsin

PSC Docket Number 1-AC-231

Announced March 16, 2010
 
WIND SITING COUNCIL

Tom Green, Wind developer, Wind Capitol Group, Dane County

Bill Rakocy, Wind developer, Emerging Energies of Wisconsin, LLC, Wind developer, Dane County

Doug Zweizig,  P&Z Commissioner, Union Township, Rock County

Lloyd Lueschow, Green County Board Supervisor, District 28, Green County,
 
Andy Hesselbach,
Wind project manager, We Energies, Dane County
 
Dan Ebert,
Vice President of Policy and External Affairs, WPPI Energy, Dane County

Michael Vickerman
, Executive Director, RENEW Wisconsin, Madison, Dane County
 
Ryan Schryver
, Global Warming Specialist, Organizer, Advocate: Clean Wisconsin, Madison, Dane County

George Krause Jr.
Real estate broker: Choice Residential LLC, Manitowoc County

Tom Meyer,
Real Estate Agent, Restaino & Associates, Middleton, Dane County

Dwight Sattler
Landowner, retired diary farmer, Malone, Fond du Lac County

Larry Wunsch,
Landowner, fire-fighter, non-participating resident of Invenergy Forward Energy wind project, Fond du Lac County
 
David Gilles,
attorney specializing in energy regulatory law, shareholder, Godfrey & Kahn Attorneys at Law, Madison, Dane County

Jennifer Heinzen, Wind Energy Technology Instructor, Lakeshore Technical College, Manitowoc County, and President of RENEW Wisconsin, Madison, Dane County
 
Jevon McFadden
University of Wisconsin, School of Medicine & Public Health, Dane County

NOTE FROM THE BPWI RESEARCH NERD:

Questions are being raised about the PSC's appointment of the President of RENEW Wisconsin as well the the Executive Director of RENEW Wisconsin. For those wonder why RENEW has two top representatives on the siting council, why not contact the PSC and ask? We'd appreciate hearing any answers they give you. CLICK HERE TO CONTACT US

Also, we can't help noting that of the 15 members on the siting council, ten of them are from Dane County. There are 72 counties in the state of Wisconsin.

In the news:

TOUGH TASK AWAITS WIND SITING COUNCIL

SOURCE: www.jsonline.com

Thomas Content

March 17, 2010

The controversial decision about how close wind turbines should be placed from homes is now in the hands of the Wisconsin Wind Siting Council.

Homeowners who live near wind turbines built in some wind farms in Wisconsin have complained about the turbines and effects including shadow flicker and noise.

The council, appointed Tuesday by the state Public Service Commission, was set up as part of a law that passed last year to set up uniform wind siting standards for the state.

The legislation came in response to local ordinances that wind developers contended amounted to virtual outright bans on wind development. Some counties and local governments also enacted wind-development moratoriums. That stalled development of small wind farms across the state, with some developers saying they were looking to develop wind power projects outside the state.

Concerns from property owners led the Public Service Commission last fall to limit how far turbines could be located from properties in the Glacier Hills Wind Park to be built by We Energies.

More recently, concerns about living near turbines have led to nearly 200 public comments in concerning Chicago-based Invenergy’s proposal to build a big wind farm south of Green Bay in Brown County.

Two members of the council have ties to the PSC, including former chairman Dan Ebert, now with WPPI Energy, and David Gilles, former commission lawyer, now with Godfrey & Kahn. Other panel members hail from utilities, wind developers and local governments that have wrestled with development of local wind siting ordinances.

In a statement Tuesday, Eric Callisto, PSC chair, said, “Wind siting regulation is complex and sometimes controversial. I look forward to the Council’s input as we develop these rules for Wisconsin.”

SECOND FEATURE

Brown County wind farm could be slowed by new state rules

Source: Green Bay Press-Gazette, www.greenbaypressgazette.com

Scott Williams

March 17 2010

The developer of a proposed Brown County wind farm said today the project could be slowed by a move to establish new statewide standards for wind farms.

Kevin Parzyck, project manager for Invenergy LLC, said the company already is adjusting its plans to account for standards imposed by state regulators on another wind project — with wind turbine setbacks of 1,250 feet from surrounding properties rather than the 1,000 feet originally planned by Invenergy.

If a new state advisory group recommends statewide standards before Invenergy’s project is under way, Parzyck said, that could require more adjustments.

“We’re moving down some parallel paths here,” he said during a meeting with the Green Bay Press-Gazette editorial board.

The state Public Service Commission on Tuesday named a 15-member advisory group to consider whether Wisconsin should set uniform policies regarding the construction of wind farms.

Invenergy submitted a proposal last fall to build Brown County’s first major commercial wind farm in the towns of Morrison, Holland, Glenmore and Wrightstown.

Once the firm’s application is deemed complete — the adjustments are under way — state regulators will have six months to hold public hearings and render a decision.

WANT MORE? CLICK HERE TO READ TODAY'S "WIND TURBINES IN THE NEWS" What did the wind developer say to the 1000 people in a bad mood?

WARRING OVER WIND-

"With well over 1,000 people in attendance – and most of them in an unpleasant frame of mind – a public information session about the proposed Belwood Wind Farm project was held at the Lions Hall in Belwood on Tuesday, Mar 9."