Entries in wind farm eminent domain (2)
3/6/11 Granting the power of Eminent Domain: Will lawmakers give wind developers just what it takes to take what you have?
FROM MONTANA
SENATE COMMITTEE HEARS TESTIMONY ON EMINENT DOMAIN BILL
SOURCE Great Falls Tribune, www.greatfallstribune.com
March 4 2011
KARL PUCKETT,
“They’re cheapskates and a foreign company trying to beat these farmers and ranchers,” said Quick, who said he was representing 10 angry cattle ranchers — eight Republicans and two Democrats — who oppose HB198.
Energy development and private property rights sharply clashed Thursday in a hearing before the Senate Energy and Telecommunications Committee over a bill that would allow developers of “merchant” transmission lines to take private land for the public good.
Testimony over House Bill 198, which had its first hearing in the Senate after previously being approved in the House, lasted more than three hours, with dozens of residents and informational witnesses speaking.
If the bill is passed, “a person” issued a certificate under the Major Facilities Citing Act to build transmission lines or other large infrastructure would have the right to initiate condemnation proceedings.
A decision last year by a Glacier County District Court judge who ruled Toronto-based Tonbridge Power Inc. did not have the authority to use eminent domain prompted the legislation. Tonbridge is building the 215-mile Montana Alberta Tie Line merchant transmission line between Great Falls and Lethbridge, and the ruling stalled the project.
With a merchant line, the developer accepts the risk of the project rather than ratepayers of a public utility, such as NorthWestern Energy. Merchant line developers finance construction by selling shipping rights to the line. In Tonbridge’s case, it sold capacity to wind farm developers who want to ship electricity generated in Montana to bigger markets.
Landowners see the bill as a change in state law for a single company, as well as a general expansion of eminent domain powers.
“This is just a sweetheart deal for a Canadian company, and allows them to condemn Montana farmland for their own use — and that’s just absolutely wrong,” said Larry Martin, a farmer from Conrad who owns land in path of MATL.
John Alke, an attorney representing Tonbridge and Montana Dakota Utilities, said the Glacier County judge’s ruling was only the second time a Montana court applied an “entity specific” standard to prevent an out-of-state developer from using eminent domain.
The first time, in 1907, the Legislature quickly passed a law ensuring a company’s eminent domain powers in building Hauser Dam, he said.
What matters in determining whether an entity has eminent domain power, Alke said, is whether the project benefits the public, not the type of entity doing the work.
If HB198 does not pass, “my client, MATL, is in serious trouble,” Alke said.
“It is in the middle of construction,” he said. “It has crews in the field.”
Derek Moretz, with wind farm developer NaturEner, said his company’s proposed $700 million Rim Rock Wind Farm in Glacier and Toole counties will not be built if MATL is not completed. Any holdup in building the line also could delay the wind farm because federal production tax credits are set to expire in 2012, he said.
“Without this eminent domain tool, we’re just not going to be able to develop these linear infrastructure projects,” said Brett Doney, president of Great Falls Development Authority.
Rep. Ken Peterson, R-Billings, the bill’s sponsor, said the bill doesn’t overhaul the current eminent domain law, but rather clarifies who can use it, including NorthWestern Energy.
Opponents of the bill disagreed with Peterson’s characterization, saying the Legislature never previously granted eminent domain power to a merchant line developer.
“This bill has a narrow motivation with broad affects,” said Beth Kaeding of Bozeman, past chair of the Northern Plains Resource Council.
Lyle Quick traveled to the hearing from Circle in Eastern Montana, where the Keystone XL pipeline is proposed, in order to testify. The line, being developed by TransCanada, would ship oil from Canada to the Gulf Coast, and Quick said HB198 could carry ramifications for that project as well.
“They’re cheapskates and a foreign company trying to beat these farmers and ranchers,” said Quick, who said he was representing 10 angry cattle ranchers — eight Republicans and two Democrats — who oppose HB198.
The Republicans are mad because “we are a party of property rights,” he said. The Democrats are mad because Gov. Brian Schweitzer, also a Democrat, supports the pipeline.
Some residents with land along MATL testified Thursday that they have been treated poorly by Tonbridge in negotiations. They urged lawmakers to vote against HB198.
Residents identifying themselves as tea party representatives, noting the state’s strong property rights protections, also spoke against the legislation. Union representatives spoke in favor of HB198, citing the jobs the projects would create.
Sen. Jim Peterson, R-Buffalo, said supporters of both natural resource development and private property rights are “caught in a vice” as a result of the controversy.
Jim Peterson spoke in favor of the bill, saying shipping electricity out of state is in the public interest, and comparing it to farmers exporting wheat.
“It might not be in Montana, but it is public use just like food is public use,” he said.
Katrina Martin, who lives east of Dutton near the MATL line route, took exception to Jim Peterson’s export comparison during her testimony.
“Yes, I export my wheat,” Martin said. “But I do not get to condemn my neighbor’s property to do it.”
2/25/10 Wind Project Picture of the day AND Knock Knock. Who's there? It's the same We Energies representative you've already said no to three times this week AND What about that meeting in Brown County?
Construction of Wisconsin's largest wind farm put on hold as WEPCO struggles to find willing landowners: use of eminent domain may be only option.
A resident in Columbia county has contacted Better Plan to say We Energies representatives are scrambling to find enough landowners willing to sign the easements needed to begin construction on the Glacier Hills wind project which is set to occupy the Columbia County Towns of Randolph and Scott. The 90 turbine project which was recently approved by the Public Service Commission, would be the largest in the state.
We Energies representatives are reportedly offering residents a signing bonus of $5000 for completion of contract paperwork by February 28th. The contracts offer landowners a yearly payment of $2,000 with a 2% annual increase. Residents report these numbers can vary widely depending on the importance of a particular easement to the project.
The easements would give We Energies permission to create turbine noise that will exceed the limits set for homes by the PSC. The easements would also allow such things as trenching for laying cables and transmission lines needed to connect the turbines along with other rights We Energies may need. The duration of a contract of this sort is usually a minimum of 40 years and runs with the land.
Some residents who have refused to sign contracts say they are still being hounded by We Energies representatives who won’t take no for an answer.
“They’ve tried to make contact with me three times already in the last several days” says Kristine Novak, whose home would be inside of the project. “They are going house to house.”
We Energies representatives may not find a lot of welcoming faces in a sharply divded community still reeling from the PSC’s decision to approve the project.
“I guess the best way to describe the feeling in the area is shock,” said the resident who wished to remain anonymous. “Hard feelings that developed earlier have now become worse.”
Those hard feelings may well extend to the We Energies Representatives who are now desperate to make deals. Says the resident, “Landowners are telling them to ‘get the hell off my property.”
He believes the tension in the community is so high that should We Energies decide to force the project through by use of eminent domain the consequences would be serious. “People around here will only take so much,” he said.
Better Plan invites residents affected by the Glacier Hills wind project to contact us with their stories.
We hope reporters in our state will follow up on this news-tip and find out more.
SECOND FEATURE:
Public Airs Concerns and Support at Wind Energy Meeting
Feb 19, 2010A Chicago company wants to build wind turbines on towers 400 feet tall in southern Brown County, using private land in Morrison, Hollandtown, Wrightstown, and Glenmore. If it's fully realized, it would become the largest wind farm in the state.
Those fighting the project held an informational meeting Thursday night, and hundreds showed up. Emotions ran high in the meeting.
"This is an industrial factory that's being dropped over some of the best farm land in Brown County," Sandra Johnson said.
"Wind is a good thing. I'm not against wind energy, we're just against the locations right now. We need to have some better setbacks and in a lot less-populated communities," David Vercauteren of Greenleaf said.
The Ledge Wind Energy Farm would be a 150-megawatt project with roughly 100 turbines.
Those backing it say it would give the county a big financial boost.
"This is a project that offers tremendous benefits in terms of new tax revenue to the county, helping farmers who were struggling, with jobs," Barnaby Dinges of Invenergy said.
Still, those who live nearby raised fears of stray voltage, shadow flicker, and noise issues.
Some say if it's built, they'll leave.
"If they go up as they're predicting, we very likely will move," Johnson said. "The problem is, land depreciates once you're in that turbine ghetto. People don't want to come. People aren't interested in buying it."
Right now the Wisconsin Public Service Commission is taking comments on the project. A public hearing will take place later this spring.
If approved, construction will likely start in 2011.